Shop drawings are the detailed drawings a fabricator, contractor or supplier prepares to show exactly how an item will be made and installed. They take the architect’s and engineer’s design and add everything the workshop needs: every dimension, part, connection, material, finish and fixing. The builder and design team review them before anything is cut, so mistakes are found on paper instead of on site.

This guide explains what shop drawings include, how they differ from other drawings, who prepares and approves them on Australian projects, and what makes a set get approved first time. The examples are anonymised extracts from real SolidCAD drawing packages.

Shop drawings vs design, fabrication and as-built drawings

Construction projects use several kinds of drawings. They are easy to confuse because they show the same items at different stages.

Drawing typePrepared byPurposeTypical detail
Design drawings (architectural and structural)Architect, engineerShow what is to be built and the performance requiredLayouts, member sizes, design loads, typical details
Shop drawingsFabricator, contractor or their drafterShow how a specific item will be made and installed, for review and approvalEvery part, dimension, connection, material and fixing
Fabrication drawingsFabricator or their drafterWorkshop information issued after approvalPart drawings, cut lists, flat patterns, weld and hole details, CNC or laser files
As-built drawingsContractor or drafterRecord what was actually builtFinal dimensions and changes made during construction

For a closer look at the first two, see shop drawings vs design drawings. For workshop-level drawings, see our fabrication drawings service.

What a complete set of shop drawings includes

The content depends on the trade, but a set that can be approved and built from usually contains:

Elevation of a 3600 mm balustrade run with typical bay, picket spacing and parts list
Run elevation with typical bay, picket spacing and part marks (balcony balustrade package)
Cut list for a steel picket balustrade with lengths, quantities and masses
Cut list with lengths, quantities and masses, so the workshop can order and cut stock

Who prepares shop drawings, and who approves them?

On most Australian commercial projects the responsibilities split like this:

Review does not transfer responsibility. The designer remains responsible for the design. The party that prepared the shop drawings remains responsible for their accuracy and for coordinating dimensions. Structural steel shop drawings, for example, must reflect the engineer’s design and the project’s nominated standards, such as AS/NZS 5131 for structural steelwork fabrication and erection.

The shop drawing approval process, step by step

  1. Collect the information. Current architectural and structural drawings, the specification, supplier data and any site measurements.
  2. Draft the package. The drafter raises queries (often as RFIs) where the design is unclear or conflicts, rather than guessing.
  3. Issue for review. Drawings are submitted with a revision letter and a clear status such as “For approval”.
  4. Review and mark-up. Reviewers return the drawings with a status, commonly: Approved, Approved as noted (proceed, incorporating the comments), or Revise and resubmit.
  5. Revise. Changes are made, clouded and recorded in the revision table, then resubmitted if required.
  6. Issue for construction or fabrication. The approved revision is issued to the workshop, often with part drawings, cut lists or CNC files.
Steel roof connection details drawing extract
Connection details from a structural steel roof package: the part reviewers check most closely

Shop drawings by trade

TradeWhat the shop drawings focus onLearn more
Structural steelMember sizes and marks, connections, bolts, welds, base plates, erection marks; often modelled in Tekla or Advance Steel, with Revit coordinationSteel shop drawings guide · Steel detailing
Balustrades, stairs and handrailsSet-out, run elevations, post and fixing details, rail and picket spacing, cut listsBalustrade shop drawings
Sheet metalFlat patterns, bend lines, hole and slot positions, material and thickness, DXF files for laser cuttingSheet metal and DXF drawings
Mechanical and manufactured partsPart and assembly drawings, tolerances, exploded views, bills of materialsMechanical drafting
Joinery and cabinetryPlans, elevations, sections, materials, hardware and installation detailsJoinery shop drawings guide
Facades, windows and architectural metalworkPanel layouts, frame details, schedules, junctions with the buildingArchitectural shop drawings
MEP servicesCoordinated duct, pipe and cable tray routes, sections and penetrationsMEP shop drawings
ReinforcementBar marks, bending schedules, placing drawingsRebar shop drawings guide
Fabrication drawing of a folded steel fire grate with lay-flat cut profile and folded views
Sheet metal: lay-flat cut profile and folded views, ready for laser cutting and folding

Why shop drawings get rejected (and how to avoid it)

What to send your drafter

Approval is fastest when the drafter starts with complete information:

Cost depends on scope, complexity and the quality of the information. See what affects the cost of shop drawings.

Frequently asked questions

What is a shop drawing?

A shop drawing is a detailed drawing prepared by a contractor, fabricator, supplier or their drafter that shows exactly how an item will be made and installed: dimensions, materials, connections, finishes and fixing. It turns the design team’s drawings into information a workshop can build from.

Who prepares shop drawings?

The trade contractor or fabricator responsible for the item prepares them, either in-house or through an outsourced drafting company. The architect and engineer do not usually prepare them; they review them.

Who approves shop drawings?

The builder or head contractor normally reviews them first and submits them to the architect and engineer, who check them against the design intent and the engineering requirements. Responsibility for the design stays with the designer; responsibility for the accuracy of the shop drawings stays with the party that prepared them.

What is the difference between shop drawings and design drawings?

Design drawings show what is to be built and the performance required. Shop drawings show how a specific item will be fabricated and installed, with every part, dimension and connection needed by the workshop.

Are shop drawings the same as fabrication drawings?

They overlap. Shop drawings are submitted for review and approval; fabrication drawings are the workshop-level drawings (part drawings, cut lists, flat patterns, CNC or laser files) issued after approval. On smaller packages one set often serves both purposes.

How long do shop drawings take?

It depends on the size of the package and how complete the design information is. A single balustrade run or gate can be quick; a full structural steel package takes longer. Most delays come from missing or conflicting information and slow review rounds, not the drafting itself.

Need shop drawings prepared?

SolidCAD prepares shop drawings and fabrication drawings for Australian fabricators, builders and manufacturers: structural steel, balustrades and stairs, sheet metal and DXF, mechanical parts, joinery and architectural metalwork. We prepare drawings only, from your design information, issued for approval and then for fabrication. Send your drawings and we will confirm the scope and turnaround.